Agenda:

Monday July 22st

11:00-11:10 INTRODUCTION R. Battiston
PARALLEL SESSIONS
11:10-13:00 PRODUCTION
Satus at COLYBRIS R. Della Marina
Status at IRST Belluti
Report from SELMIC visit N. Dinu
Silicon tests status N. Dinu
Procurement Status M. Pauluzzi / C. Cecchi
Status of AR Sensors W. Wallraff
Discussion: Next 12 months plan
Production phase 2, procedures and
infrastructure
P. Azzarello
11:10-13:00 ELECTRONICS
Tracker Electronics: system review Ambrosi, Cortina, Hass, Menichelli, Puccini, Tintori
TDR status Cortina/Hass
Power Supply status M. Menichelli
Report from last TRD/TRK Electronic meeting G. Ambrosi
13:00-14:30 Lunch  
14:30-16:30 MECHANICS and ALIGNEMENT  
  Tracker mechanics E. Perrin
  Update on alignement system W. Wallraff
  Metrology results B. Burger
16:30-17:00 Coffee  
17:00-18:00 Results from cosmic test bench Cristinziani
Cable test Rapin
Short info on Catania test beam D. Caraffini
19:00 Dinner  


Tuesday July 23nd

9:00-11:00 TEST BEAM PREPARATION  
  DAQ system D. Haas
  Beam composition and characteristics E. Cortina
  Test ladders, program and analysis P. Azzarello
Common discussion on the overall organization  
11:00-11:30 Coffee  
11:30-12:00 Summary of monday parallel sections M.Pauluzzi, G.Ambrosi
12:00-12:30 Tracker NIM paper W. Burger
12:30-14:00 Lunch  
14:00-16:00 PHYSICS  
  Photon sensitivity estimates and source
generator
S. Natale
  Search for ACR in AMS-01 data V. Choutko
16:00-16:30 CONCLUSIONS AND ACTION ITEMS  
16:30-17:00 Reserved  

Please contact us for comments/suggestions on the schedule.


Regards

Roberto Battiston               Giovenni Ambrosi